The
Rush Creek Project widened 7 miles of existing 2-lane highway to a
4-lane divided highway in and near the community of Lee Vining.
Construction components of the project included:
two bridges at Rush Creek; concrete box culverts at Walker, Parker,
and Lee Vining Creeks; and retaining walls on both sides of Highway 395 at
the south entrance to Lee Vining.
The project began in the early 1990s,
and the environmental review was released in August 1997.
Caltrans determined this project would not have a significant
effect on the environment and issued a Negative Declaration. The Federal Highway Administration concurred, and an Environmental
Impact Statement was not required.
Construction began summer 2000.
The scope of the project appeared to be exceeding any previously
communicated plans. In public
meetings, Caltrans repeatedly denied that variations to the original plan
were occurring. Only when the
community repeatedly questioned the project, did Tom Hallenbeck - District
9 Caltrans Director - admit to a list of 11 discrepancies
from the original plan.
As a result of the admitted
discrepancies, Mono County has increased its involvement with the Rush
Creek Project. It assigned
John Wohlmuth - Mono County Chief Administrative Officer - the task of
negotiating additional mitigation to compensate for the increased
disturbance. Mono County has
agreed to discuss the additional mitigation with the Committee prior to
acceptance.
